Steel-Cutting Ceremony for the hybrid ferry (Building Number P315)

published: 02.07.2020

The Steel-Cutting Ceremony of the next hybrid double ended ferry (project no P315) for Finferries was held in CRIST Shipyard, Poland on July 1th, 2020.

Due to coronavirus pandemic only Shipyard and DNV representatives witnessed the milestone.

P315-ciecie blach_1

The LMG Marin, well known design office, is responsible for design of the ferry.

StoGda supports LMG Marin in Basic Design documentation and is responsible for delivery complete Workshop Documentation and As Built Documentation to the yard. StoGda has also supervise the building.

Planned delivery date of the vessel: January 2022.